Davis Gap Transmission Project
Transmission Line
Miles:
2.5
Website:
https://www.tva.com/Energy/Tra...
Percent Operating:
0.0% (0.0 of 2.5 mi.)
Segments Operating:
0 of 1
Description:
TVA is proposing to build about 2.5 miles of single-circuit transmission line to power a new Fort Payne Improvement Authority substation on the south end of Fort Payne. The line would begin at TVA’s existing Fort Payne-Collinsville 161-kV Transmission Line and extend east to the new Davis Gap Substation to be located on the northeast corner of the intersection of Lebanon Road and U.S. Highway 11.
Contacts:
Title
Company
E-mail
Phone
Transmission Siting Engineer
Tennessee Valley Authority (TVA)
•••••••••••••
•••••••••••••
Project Manager
Tennessee Valley Authority (TVA)
•••••••••••••
•••••••••••••
Analyst Notes:
Project Documents:
Davis Gap Transmission Project Map
Key Dates:
Companies Involved:
Company Name
Company Role
Tennessee Valley Authority (TVA)
•••••••••••••
Tennessee Valley Authority (TVA)
•••••••••••••
Segments:
Name
Voltage
Miles
Status
Davis Gap - Payne-Collinsville Tap
161 kV
2.5 mi
Pre-Construction
Owner:
Tennessee Valley Authority (TVA)
Developer:
Tennessee Valley Authority (TVA)
Line Location:
Above Ground
Development Timeline:
Time of Change
Year of Change
Status
Confirmed
January
2023
Operating
January
2023
Under Construction
Locations:
County
State/Province
Country
De Kalb
AL
USA
Stations:
Type
Voltage
Status
Payne-Collinsville Tap
Tap Line
Operating
Davis Gap
Substation
161 kV
Operating