Nevill Road-Greasewood Solar Transmission Line Project
Transmission Line
Miles: 10.0
Percent Operating: 0.0% (0.0000 of 10.0 mi.)
Segments Operating: 0 of 1

Description: In order to connect the proposed Greasewood Solar Project, Garland Power & Light is proposing construct 10 miles of 345 kV transmission line between the Nevill Road Switch and Greasewood Substations.

Contacts:
TitleCompanyE-mailPhone
Transmission Engineer Garland Power & Light ••••••••••••• •••••••••••••


Analyst Notes:


Key Dates:

Companies Involved:
Company NameCompany Role
Garland Power & Light •••••••••••••
Garland Power & Light •••••••••••••
Burns & McDonnell •••••••••••••
Segments:
 NameVoltageMilesStatus
Nevill Road-Greasewood Solar345 kV10.3 miPre-Construction - Chosen Route