Shoshone-Glenwood Electrical Upgrades Project
Transmission Line
Miles: 8.0
Website: https://www.transmission.xcele...
Percent Operating: 0.0% (0.0000 of 8.0 mi.)
Segments Operating: 0 of 1

Description: Xcel Energy will be replacing and repairing transmission and distribution structures over the summer and fall of 2019 in the Glenwood Canyon and in areas within the White River National Forest. The work will take place between the Shoshone Hydroelectric Plant and the City of Glenwood Springs between June and October.

This work is important to maintaining a reliable electric system for the area now and in the future. Some of the transmission structures have reach their end-of-life use, with many dating back to initial placement in the early 1900s. Approximately 30 transmission structures and approximately 10 distribution structures will be replaced during the effort.

Contacts:
TitleCompanyE-mailPhone
Chairman, President and Chief Executive Officer Public Service Company of Colorado ••••••••••••• •••••••••••••


Analyst Notes:

Project Documents:

Key Dates:

Companies Involved:
Company NameCompany Role
Public Service Company of Colorado •••••••••••••
Public Service Company of Colorado •••••••••••••
Segments:
 NameVoltageMilesStatus
Shoshone-Glenwood69 kV6.3 miUnder Construction