Irvington-East Loop Transmission Line
Transmission Line
Miles: 12.8
Website: https://www.tep.com/irvington-...
Percent Operating: 0.0% (0.0000 of 12.8 mi.)
Segments Operating: 0 of 3

Description: Tucson Electric Power (TEP) is developing plans for a new transmission line to help serve growing energy needs. The project would help Davis-Monthan Air Force Base satisfy its energy resiliency requirements and improve electric reliability for customers in Tucson.

Contacts:
TitleCompanyE-mailPhone
Director, Transmission and Distribution Planning Tucson Electric Power (TEP) ••••••••••••• •••••••••••••
Chief Information Officer & Vice President of Energy Delivery & Safety Tucson Electric Power (TEP) ••••••••••••• •••••••••••••
Manager, Transmission Control Tucson Electric Power (TEP) ••••••••••••• •••••••••••••
Manager, Transmission Planning & Transmission Planning Engineer Tucson Electric Power (TEP) ••••••••••••• •••••••••••••
Manager, Transmission & Distribution System Control Tucson Electric Power (TEP) ••••••••••••• •••••••••••••


Analyst Notes:


Key Dates:

Companies Involved:
Company NameCompany Role
Tucson Electric Power (TEP) •••••••••••••
Tucson Electric Power (TEP) •••••••••••••
Segments:
 NameVoltageMilesStatus
Irvington-Port138 kV4.0 miPre-Construction - Planned Route
Port-Patriot138 kV3.0 miPre-Construction - Planned Route
Patriot-East Loop138 kV4.0 miPre-Construction - Planned Route